Non Slip Glaze Surface Rate Topic: -----

#1 User is offline   pottyjac Icon

  • Newbie
  • Pip
  • Group: Members
  • Posts: 4
  • Joined: 28-July 10
  • LocationCumbria, England

Posted 28 July 2010 - 12:36 PM

Hi there,

I wonder if anyone can help. I have just completed a 6 foot diameter ceramic mural for a local school, which I designed and made to be installed on an incline. This is now glazed and I am about to finish and fire in some decals of the children's drawings. The architect has now 'moved the goal posts' and the mural is to be installed flat and be walked upon. This now presents health and safety implications as it could be slippy when wet.

Has anyone encountered this before and could advise me how I could proceed to solve the problem now presented. One solution I was thinking could be to refire but with a fine covering of silver sand to put some tooth into the existing clear glaze. The mural is made of 110 individually made sections, some are carved/impressed and others are smooth.

Any suggestions would be very appreciated.
0

#2 User is offline   Chris Campbell Icon

  • Advanced Member
  • PipPipPip
  • View gallery
  • Group: Members
  • Posts: 1,364
  • Joined: 07-April 10
  • LocationRaleigh, NC

Posted 29 July 2010 - 09:46 AM

Sorry but I have no solutions other than to encourage you to protect yourself.

In writing, make sure the architect understands the risks then, hopefully, you
will not be liable for any injuries.
Chris Campbell
Contemporary Fine Colored Porcelain
www.ccpottery.com

"My Artwork would not exist without a thriving global pottery community.
In the isolation of a studio, an artist can begin to feel like an island, but in truth
we are all part of archipelagoes; chains of islands loosely connected by a stream
of information that enhances our Artwork.”
0

#3 User is offline   Marcia Selsor Icon

  • Advanced member
  • PipPipPip
  • View gallery
  • Group: Members
  • Posts: 2,431
  • Joined: 16-May 10
  • LocationBrownsville, TX

Posted 30 July 2010 - 03:25 AM

I agree with Chris. If this was not the original plan for the design's installation, someone has just made a hazardous slippery situation. Make sure you are not liable. In writing.
Marcia
Marcia Selsor
0

#4 User is offline   Seasoned Warrior Icon

  • Businessman - Potter
  • PipPipPip
  • View gallery
  • Group: Members
  • Posts: 294
  • Joined: 02-April 10

Posted 30 July 2010 - 04:14 PM

View Postpottyjac, on 28 July 2010 - 10:36 AM, said:

Hi there,

I wonder if anyone can help. I have just completed a 6 foot diameter ceramic mural for a local school, which I designed and made to be installed on an incline. This is now glazed and I am about to finish and fire in some decals of the children's drawings. The architect has now 'moved the goal posts' and the mural is to be installed flat and be walked upon. This now presents health and safety implications as it could be slippy when wet.

Has anyone encountered this before and could advise me how I could proceed to solve the problem now presented. One solution I was thinking could be to refire but with a fine covering of silver sand to put some tooth into the existing clear glaze. The mural is made of 110 individually made sections, some are carved/impressed and others are smooth.

Any suggestions would be very appreciated.




Hi:

I am sorry that you have encountered this problem but while I have no technical suggestions to offer I do have some considerations you could consider. I have had changes made by the customer in the past but I always have a contract for cutom work. I am not an attorney so I can not give you advice but I can tell you what I have done under similar circumstances. I have a contract that spells out the technical specifications for the project as well as a technical drawing of the location and a drawing showing the art. The contract is agreed to by all parties at a multi-disciplinary meeting with the architect and the contractor and myself. I have needs that the contractor needs to understand for my project. If there are any changes then I require a change order. I would consider going from a sloped installation to a level installation with people walking on my art is a material change. I would develop the specification for the change and then I would charge appropriately for it. A material change may actually require new art or substantial changes to the existing art but the changes should be well documented and the artist should be adequately compensated.

Good luck and best regards,
Charles
0

#5 User is offline   pottyjac Icon

  • Newbie
  • Pip
  • Group: Members
  • Posts: 4
  • Joined: 28-July 10
  • LocationCumbria, England

Posted 01 August 2010 - 04:05 PM

View PostChris Campbell, on 29 July 2010 - 09:46 AM, said:

Sorry but I have no solutions other than to encourage you to protect yourself.

In writing, make sure the architect understands the risks then, hopefully, you
will not be liable for any injuries.



Thanks you very much for getting back to me. Am in the UK and this is first time used forum. Cheers Jac.
0

#6 User is offline   pottyjac Icon

  • Newbie
  • Pip
  • Group: Members
  • Posts: 4
  • Joined: 28-July 10
  • LocationCumbria, England

Posted 01 August 2010 - 04:07 PM

View PostMarcia Selsor, on 30 July 2010 - 03:25 AM, said:

I agree with Chris. If this was not the original plan for the design's installation, someone has just made a hazardous slippery situation. Make sure you are not liable. In writing.
Marcia





Thanks Marcia, I will certainly do that. Cheers Jac
0

#7 User is offline   pottyjac Icon

  • Newbie
  • Pip
  • Group: Members
  • Posts: 4
  • Joined: 28-July 10
  • LocationCumbria, England

Posted 01 August 2010 - 04:25 PM

View PostSeasoned Warrior, on 30 July 2010 - 04:14 PM, said:

View Postpottyjac, on 28 July 2010 - 10:36 AM, said:

Hi there,

I wonder if anyone can help. I have just completed a 6 foot diameter ceramic mural for a local school, which I designed and made to be installed on an incline. This is now glazed and I am about to finish and fire in some decals of the children's drawings. The architect has now 'moved the goal posts' and the mural is to be installed flat and be walked upon. This now presents health and safety implications as it could be slippy when wet.

Has anyone encountered this before and could advise me how I could proceed to solve the problem now presented. One solution I was thinking could be to refire but with a fine covering of silver sand to put some tooth into the existing clear glaze. The mural is made of 110 individually made sections, some are carved/impressed and others are smooth.

Any suggestions would be very appreciated.


.



Hi:

I am sorry that you have encountered this problem but while I have no technical suggestions to offer I do have some considerations you could consider. I have had changes made by the customer in the past but I always have a contract for cutom work. I am not an attorney so I can not give you advice but I can tell you what I have done under similar circumstances. I have a contract that spells out the technical specifications for the project as well as a technical drawing of the location and a drawing showing the art. The contract is agreed to by all parties at a multi-disciplinary meeting with the architect and the contractor and myself. I have needs that the contractor needs to understand for my project. If there are any changes then I require a change order. I would consider going from a sloped installation to a level installation with people walking on my art is a material change. I would develop the specification for the change and then I would charge appropriately for it. A material change may actually require new art or substantial changes to the existing art but the changes should be well documented and the artist should be adequately compensated.

Good luck and best regards,
Charles


Many thanks for taking the time to reply in so much detail. Thank you for sharing your practice and how you would approach a similar contract. I have a background in insurance and English law (a former life!) and I can't believe I am not taking control appropriately as there has clearly been a material change to the original contract. I have since done some research and there is a substance you can apply to ceramic tiles to make them non-slip but it needs applied yearly.

I will make it a written condition that installation is subject to the School taking over all responsibility for ensuring the surface is regularly treated and absolute liability rests with them.
Kind regards, jac
0

#8 User is offline   nicoledc109 Icon

  • Newbie
  • Pip
  • Group: Members
  • Posts: 1
  • Joined: 03-August 10

Posted 03 August 2010 - 05:21 AM

View Postpottyjac, on 28 July 2010 - 12:36 PM, said:

Hi there,

I wonder if anyone can help. I have just completed a 6 foot diameter ceramic mural for a local school, which I designed and made to be installed on an incline. This is now glazed and I am about to finish and fire in some decals of the children's drawings. The architect has now 'moved the goal posts' and the mural is to be installed flat and be walked upon. This now presents health and safety implications as it could be slippy when wet.

Has anyone encountered this before and could advise me how I could proceed to solve the problem now presented. One solution I was thinking could be to refire but with a fine covering of silver sand to put some tooth into the existing clear glaze. The mural is made of 110 individually made sections, some are carved/impressed and others are smooth.

Any suggestions would be very appreciated.


Thanks for sharing.


__________________
Watch The Other Guys Online Free
0

Page 1 of 1
  • You cannot start a new topic
  • You cannot reply to this topic

1 User(s) are reading this topic
0 members, 1 guests, 0 anonymous users